Denmark East Development Precinct Project

Announcement of Successful Grant

The Minister for Lands and Regional Development, Hon Terry Redman MLA,  announced $7.6 million in funding from the Royalties for Regions fund for the development of the industrial area, a second bridge crossing point over Denmark River and the associated connector roads.

The Council at its meeting on Tuesday 22nd March 2016 accepted the grant funding and appointed LandCorp to undertake the project management works to deliver this project(Council Resolution  280316).

LandCorp Project Information Sessions

On Tuesday 5 May 2016 LandCorp held a series of Project Information Sessions and gave a presentation outlining the different stages of the project and the consultation process that would occur.

EAST RIVER ROAD EXTENSION (Western Precinct) - DENMARK RIVER BRIDGE Community Consultation and Information Session

Background FAQs

Click on the above link to download some responses to Frequently Asked Questions.

Community Consultation - Western Precinct

Click on the below links to download the Reports, Fact Sheets, FAQs and Submission Form in relation to the proposed options for the Denmark River Bridge crossing point, including the associated road connection from East River Road to Scotsdale Road and the intersection treatment on the Denmark - Mt Barker Road.

Arborist Report

Heritage Report

Phase 1 - Options Analysis

Flora & Fauna Report

Fact Sheet 1 - Background

Fact Sheet 2 - Environmental, Aboriginal Heritage & Engineering Report Summaries 

Fact Sheet 3 - Denmark/Mt Barker Road Intersection Treatment Options  

Fact Sheet 4 - East River Road Bridge Crossing 

FAQs

Submission Form

East River Road (Eastern End) Alignment

Council endorsed the road alignment for the Eastern Precinct, which comprises the area from Denmark - Mt Barker Road to McIntosh Road and includes the proposed industrial area, at the Ordinary Meeting of Council held on 18 October 2016.

Work has recently commenced on the Denmark East Development Precinct Project (Eastern Precinct), with the Shire of Denmark utilising budgeted Roads to Recovery funding to complete approximately 1.5km of the 3.7km required road length to the industrial area, this financial year.

Works include the upgrade of the road to RAV standard, with this currently taking place on East River Road, within approved clearing permit areas, from Denmark-Mt Barker Road to Sheoak Drive.

During this time ‘through traffic’ will cease on this section of road, and access will be via the eastern section of East River Road via McIntosh Rd.

‘Road Closed’ signs will be displayed during this time and, when possible, arrangements will be made to open the road on weekends.

The Shire of Denmark is working hard to minimise all disruptions and asks users to show caution when driving on gravel roads and observe all advisory signs.

The Shire of Denmark thanks residents for their patience and cooperation during this time.

It is proposed to commence Denmark East Development Precinct Project Stage 2 in late September 2017, weather permitting for a duration of approximately 10 months.

 We are currently waiting for confirmation from Western Power and LandCorp for the timing of their projects before the Shire can schedule the different stages of work; which are as follows; 

  • Stage 1B: Denmark-Mt Barker Road intersection to (completed) Stage 1A
  • (completed)
  • Stage 2A: Between Wrightson Road and Sheoak Drive
  • Stage 2B: Sheoak Drive to McIntosh Rd
  • Stage 2C : McIntosh Road, North towards East River Road

During the road construction stages, Council will be implementing traffic management plans (TMP’s) as approved by Main Roads WA, and more detailed information will be available closer to the time.